Brooklyn’s Third Avenue Safety Redesign Targets 2028 Completion

The Sunset Park project will add median-side protected bike lanes, pedestrian islands and shorter crossings after years of delay.

Brooklyn’s Third Avenue Safety Redesign Targets 2028 Completion – New York Samuel Seelig

Brooklyn’s Sunset Park will get a 2.1-mile safety redesign of Third Avenue, with Mayor Zohran Mamdani saying work is expected to start in 2027 and finish by the end of 2028. The plan covers the avenue from 20th to 62nd streets beneath the Gowanus Expressway, adding protected bike lanes, shorter pedestrian crossings and redesigned intersections.

The city’s announcement revives a project first proposed in 2023 and put on hold in April 2025 under former Mayor Eric Adams. It comes after renewed calls from Brooklyn lawmakers following the Aug. 29 death of Jiayi Zheng, a 28-year-old nurse struck by a hit-and-run driver while crossing at 55th Street. The city says 17 people have been killed along Third Avenue in the past decade.

How the redesign will change the avenue

The Department of Transportation plans to put barrier-protected bike lanes in both directions beside the avenue’s center median. The design also includes pedestrian islands, sidewalk extensions and intersection changes intended to slow traffic. DOT says the changes could cut by up to half the distance people must cross through moving traffic.

Third Avenue is 150 feet wide, with six moving traffic lanes, two parking lanes and a median that is 52 feet wide along much of the corridor. Unlike the city’s earlier proposal, the new design places bike lanes by the median rather than at the curb. DOT Commissioner Mike Flynn said that would reduce conflicts with delivery trucks and vehicles entering businesses.

The plan also calls for a two-way, parking-protected bike lane on 60th Street between Second and Fourth avenues, connecting the Fourth Avenue bike lanes to the Brooklyn Waterfront Greenway. DOT plans to reorganize parking along the Third Avenue median, including adding metered spaces.

When work is scheduled

The first phase is scheduled to begin in 2027 between 62nd and 43rd streets. It includes the intersection at 55th Street where Zheng was killed. The second phase, from 43rd to 20th streets, is planned for 2028. Mamdani said the city expects to complete the redesigns by the end of that year.

Flynn said the first phase will address dangerous intersections, including Third Avenue and 60th Street. That intersection recorded 72 injuries, including five severe injuries, and one death over the past five years, according to the commissioner. DOT will continue refining the plan with residents before construction begins. Possible extensions south to 65th Street and north toward Carroll Street are under consideration but are not part of the current construction schedule.

This report draws on information from amNewYork.

Editorial checks passed Facts, figures and quotes checked against 1 source